Detailed-design review / connect one requirement to the next commitment

# Critical design review (CDR): checklist and exit criteria

A critical design review (CDR) assesses whether the detailed design has enough support for the project's next implementation, integration or test commitment. The decision is whether that commitment can proceed, requires an authorized condition, or should be deferred under the adopted review criteria. For software, examine how consequential requirements become states, interfaces and failure handling, and what evidence supports those choices. [NASA's CDR guidance](https://nodis3.gsfc.nasa.gov/displayDir.cfm?Internal_ID=N_PR_7123_001D_&page_name=AppendixG) and the [September 2026 defense guidebook](https://www.cto.mil/wp-content/uploads/2026/09/SE-Guidebook-2026.pdf) place this decision within a broader system review.

**Start with your own design:** name the next commitment and its governing criterion. Choose one requirement whose failure would matter to that decision. Mark a failure boundary, such as an interruption between an external action and a local record, and locate the candidate design's recovery rule. Write down what supports that rule, what is still unknown and who should resolve the gap.

[Copy the free first-review record](https://reqproof.com/topics/critical-design-review#worksheet) · [Inspect the filled failure-path example](https://reqproof.com/topics/critical-design-review#example)

The complete human worksheet is available below without signup. It supports one first-review thread; it is an original engineering aid, not an official form or a complete government CDR package.

## What you'll leave with

**A record for your own decision.** Connect the governing criterion, requirement, candidate design, evidence, owner and actual next commitment.

**A concrete documentary finding.** See why a missing dispatch record leaves recovery unresolved, without mistaking a possible failure for an observed incident.

**A check that could change the decision.** Specify the external effect and recovered local knowledge to inspect, then keep the recommendation separate from authorization.

### Five facts that matter at CDR

- **Production coding may still lie ahead.**  The September 2026 defense guidebook describes an initial product baseline mature enough for production software coding to proceed; it does not expect a complete-system demonstration at CDR. [§5.7 and Table 5-5](https://www.cto.mil/wp-content/uploads/2026/09/SE-Guidebook-2026.pdf)
- **A candidate and an approved baseline are different states.**  NASA describes final drafts entering review, followed by updates and formal baselining after approved comments. [§5.2.2.4](https://nodis3.gsfc.nasa.gov/displayDir.cfm?Internal_ID=N_PR_7123_001D_&page_name=Chapter5)
- **A missing local record does not establish that remote work never started.**  Recovery needs a justified way to resolve that uncertainty.
- **Preventing every operation cannot satisfy required work.**  Include ordinary success when assessing a proposed failure-handling design.
- **A closure plan is not self-authorizing.**  NASA and defense provisions differ; the adopted criteria and responsible authority determine what may proceed. [Inspect the review basis](https://reqproof.com/topics/critical-design-review#sources)

The official-source facts retain their stated applicability. The software observations below are illustrative design reasoning, not application results or universal exit criteria.

## What happens after completion recording fails?

**Illustrative rule: preserve one intended job for one approved request without silently losing required work.** A dispatcher asks a separate worker or service to start the job, then records locally that dispatch completed. Dispatch completion concerns the request to start work, not completion of the job itself.

  [Free CDR first-review record](https://reqproof.com/topics/critical-design-review#worksheet)

ILLUSTRATIVE DESIGN REVIEW / NOT EXECUTED

A missing dispatch record leaves the remote outcome unresolved.

Intended external effect **One intended job for one approved request, with required work preserved. This is an illustrative rule.**

Described ordering **The dispatcher asks the separate receiver to start the job, then persists a local dispatch-completion record.**

Possible interruption and restart **The receiver may have started the job before local recording fails. Restart may resend because completion is not recorded.**

Condition for an unintended repeat **The original request took effect and the receiver does not prevent another start of the same intended job.**

Documentary finding **The description does not establish recovery without an unintended repeat or lost required work.**

Illustrative design reasoning, not a captured execution. Receiver capabilities are unknown; no operation, repeat or loss was observed. Dispatch completion concerns the request to start work, not completion of the job.
 [Inspect the finding and proposed checks ↗](https://reqproof.com/topics/critical-design-review#example)

[Free CDR first-review record Copy the complete human worksheet and filled illustrative record on this page. Free, without signup.](https://reqproof.com/topics/critical-design-review#worksheet)

**Exhibit: a possible recovery sequence, not a captured execution.** The receiver's actual capabilities are unknown.

Review item / Described behavior or bounded conclusion

| Review item | Described behavior or bounded conclusion |
| --- | --- |
| Intended external effect | One intended job for one approved request, with required work preserved. This is an illustrative rule. |
| Described ordering | The dispatcher asks the separate receiver to start the job, then persists a local dispatch-completion record. |
| Possible interruption and restart | The receiver may have started the job before local recording fails. Restart may resend because completion is not recorded. |
| Condition for an unintended repeat | The original request took effect and the receiver does not prevent another start of the same intended job. |
| Documentary finding | The description does not establish recovery without an unintended repeat or lost required work. |

No operation, repeat or loss was observed. The missing support is the receiver contract and a recovery design justified against it. [Inspect the finding and proposed checks](https://reqproof.com/topics/critical-design-review#example).

01 / Define the decision

## What is a critical design review?

A software reviewer should be able to follow a requirement into the relevant interface, state transition, algorithm or durability decision, then inspect its support. Entrance criteria govern readiness to conduct the review; success or exit criteria and the applicable completion process govern its outcome. [NASA review requirements](https://nodis3.gsfc.nasa.gov/displayDir.cfm?Internal_ID=N_PR_7123_001D_&page_name=Chapter5)

The broader review also covers detailed requirements and traceability, interfaces, analyses and margins, safety and security, resource and cost/schedule constraints, configuration control, integration and V&V plans, manufacture and support where relevant, and risks or open work. The single thread in this guide teaches a method within that scope. [Defense Table 5-5](https://www.cto.mil/wp-content/uploads/2026/09/SE-Guidebook-2026.pdf) · [NASA Table G-7](https://nodis3.gsfc.nasa.gov/displayDir.cfm?Internal_ID=N_PR_7123_001D_&page_name=AppendixG)

**Different reviews answer different questions.**

Review or check / Main question / Boundary

| Review or check | Main question | Boundary |
| --- | --- | --- |
| Preliminary design review (PDR) | Can the proposed architecture meet requirements within the constraints and risks, so detailed design can proceed? | Architecture feasibility does not settle every recovery transition. |
| Critical design review (CDR) | Does the detailed design support the identified next commitment under the adopted criteria? | It does not automatically establish completed implementation, final verification or release readiness. |
| Test readiness review (TRR) | Are the candidate, procedures, people and environment ready for the specified test campaign? | Readiness to test does not mean the campaign has passed. |
| Ordinary code review | Does this source change satisfy its intended behavior and engineering expectations? | Its scope may cover only part of the design or review package. |
| Proof's configured CDR gate | Do the configured preparation checks meet their criteria? | It does not authorize a CDR outcome or semantically review every failure path. |

The lifecycle distinctions follow [NASA Appendix G](https://nodis3.gsfc.nasa.gov/displayDir.cfm?Internal_ID=N_PR_7123_001D_&page_name=AppendixG). Code review has the practical scope stated above; the [Proof boundary](https://reqproof.com/topics/critical-design-review#proof-workflow) is product-specific.

Establish applicability before borrowing a checklist. Use the actual contract, adopted lifecycle/pathway, project plan, criterion revision and authority. A small commercial team can use the worksheet to improve a design decision without asserting that NASA or defense requirements govern it. “Proceed,” “condition” and “defer” here are plain-language choices, not a replacement for your process's disposition rules.

02 / Start with the free record

## Copy a complete first-review record

Start with fields 1 through 4 using material you already have. Then write one finding and the next observation needed to resolve it. Use **UNKNOWN** for missing information, **UNASSIGNED** for an appointment that has not been made, and **NOT APPLICABLE, with a reason** where a field does not belong to the claim.

Keep a proposed check labeled **NOT EXECUTED** until a result exists. A documentary finding can be useful before implementation exists.

```text
HUMAN CDR FIRST-REVIEW RECORD

1. Governing basis and scope
Project/component and bounded review question:
Adopted criterion, source edition and project-plan revision:
Why it applies; approved tailoring, equivalents or exceptions:
Scope of this thread; related obligations reviewed elsewhere:

2. Next commitment and authority
Actual implementation, integration or test commitment being considered:
Person/role authorized to decide; appointment status:
What proceeding would commit the project to:

3. Consequential requirement and effect
Requirement identity/revision, wording, source and approval status:
Required ordinary behavior and relevant external effect:
Failure boundary and consequence of the wrong result:
Required bounds/success criteria; unresolved choices and their owner:

4. Candidate and detailed-design decision
Candidate design identity/revision and reviewed location:
Approved baseline identity/status, separately from the candidate:
Relevant state, interface, ordering and durability decision:
Meaning of acknowledgments, completion and recovered knowledge:
Dependency guarantees relied on; assumptions still unestablished:

5. Available evidence and its limit
Material actually inspected and its identity/location:
Type: design inspection / analysis / prototype or test record / proposed work:
What this evidence supports:
Missing, conflicting or stale support; limits on reuse:

6. Documentary finding
Requirement-to-design-to-evidence gap or supported conclusion:
Why it matters to the identified next commitment:
Observed behavior, if any; distinguish it from a possible failure:

7. Proposed correction and verification condition
Contract, requirement or design decision to resolve:
Proposed change and implementation status:
For each necessary check, record:
  Scenario, including ordinary success and the relevant failure boundary:
  Expected external effect and recovered local state/knowledge:
  Plausible wrong result the observation must distinguish:
  Acceptance criterion and bounds, or owner of the unresolved criterion:
  Contract/evidence prerequisites; limitations of substitutes:
  Evidence status and result location, or NOT EXECUTED:

8. Responsibility and closure
Duty owner for each action; appointed person or UNASSIGNED:
Required closure artifacts/evidence and who reviews them:
What must be available for this commitment; what belongs to later checks:
Due date or review point; unresolved scheduling decisions:
Changes that require this finding or evidence to be reassessed:

9. Recommendation and authorized disposition
Reviewer's recommendation, affected scope and proposed conditions:
Actual authority's disposition; decision record and approved scope:
Outstanding actions and their authorized treatment:
Current status; if no decision exists, write UNRECORDED:
```

Use the project review plan to cover the remaining CDR categories.

03 / Inspect the failure-path finding

## Worked example: recovery cannot infer what the receiver did

The illustrative commitment is to implement automatic recovery for the dispatcher's job-start request while preserving one intended job without silently losing required work. The actual project requirement, design revision and authority are unknown.

### What the described design leaves unresolved

Sending a request, remote acceptance, the job-start effect, receipt of a reply and durable local knowledge are distinct events. The receiver contract must explain their relationship. Even receiving a reply does not ensure that the dispatcher can recover that knowledge after its local completion write fails.

The [opening exhibit](https://reqproof.com/topics/critical-design-review#technical-specimen) shows the consequential window: the external effect may already have occurred while the durable local completion record is absent. Retrying could repeat that effect; suppressing all retries could instead abandon a request that never took effect. **The documentary finding is that the described design does not establish recovery without an unintended repeat or lost required operation.** No implementation behavior was observed.

Recording completion before sending does not resolve the problem. A crash between those steps could leave the local record saying “complete” while no job started. A durable **pending intention** means work remains owed; it must not be confused with completed dispatch.

### Proposed correction: establish the contract before selecting recovery

The proposed work is to resolve the receiver interface and revise the recovery design. It is **unimplemented**. Identify:

- What distinguishes one logical operation from a new approved request.
- How the receiver relates operation identity, duplicate handling and the intended effect atomically and durably, including applicable concurrency and retention limits.
- What acceptance, replies and status information establish; how recovery reconciles uncertain outcomes; and what happens when the available evidence cannot resolve them.
- How normal approved work still happens.

A request ID, local transaction or outbox alone does not establish one remote effect. AWS's [idempotent-API explanation](https://aws.amazon.com/builders-library/making-retries-safe-with-idempotent-APIs/) describes receiver-side obligations that make an identity useful. [RFC 9110 §9.2.2](https://www.rfc-editor.org/rfc/rfc9110.html#section-9.2.2) supplies HTTP-specific intended-effect and retry semantics. Neither establishes this receiver's facilities or creates a CDR obligation.

### Proposed observations that would distinguish recovery outcomes

**Verification plan for the illustrative rule. Every row is NOT EXECUTED.** Actual bounds, success criteria and receiver facilities remain to be established. “External effect” means the intended logical job-start operation, as defined by the adopted requirement and receiver contract.

Proposed scenario / External effect and recovered local knowledge to inspect / Plausible wrong result / Prerequisites

| Proposed scenario | External effect and recovered local knowledge to inspect | Plausible wrong result | Prerequisites |
| --- | --- | --- | --- |
| Ordinary approved request | The intended job starts once; durable dispatch status accurately reflects the agreed receiver result without claiming the job finished. | Blanket rejection, no required work, or local completion unsupported by the receiver result. | Defined operation/effect, acknowledgment meaning, observable receiver evidence and ordinary-success criteria. |
| Possible remote effect, then interruption before durable local completion recording, followed by restart | Establish whether the first request took effect. Recovery preserves that intended job without another unintended start. Local state records the supported result, or retains explicit uncertainty for an owned resolution step under the adopted recovery requirement. | An additional job starts after the first took effect, or recovery claims certainty without support. | Actual duplicate-handling/durability contract, operation correlation, applicable concurrency/retention rules and a controlled way to exercise the boundary. |
| Request or reply loss leaves the outcome uncertain | Examine both possibilities: the request took effect but the reply was lost, or no effect occurred. Recovery reconciles an applied operation or preserves and performs the still-required work, with accurate local state. | Blind retry repeats applied work; blind suppression loses unapplied work; silence is treated as proof of either outcome. | Real result/status semantics, meaningful effect observations and an agreed response when safe reconciliation is unavailable. |

Recording uncertainty does not satisfy the requirement to perform approved work. Required recovery bounds and any authorized escalation or failure disposition remain to be set.

Send counts, mock success and local record counts alone cannot establish actual receiver effects. A stub can inspect caller logic; it cannot prove an unavailable receiver guarantee. Even a “not found” status needs a contract explaining whether it establishes that the operation was never applied.

Add overlapping retries, delayed requests beyond the supported recovery horizon or changed intent under the same identity when the selected contract depends on those behaviors. Do not invent their permitted bounds.

### Complete filled illustrative record

The record below makes a bounded reviewer recommendation. It records neither an authorized hold nor a failed CDR. Which analyses or prototype results are needed before implementation, and which checks follow it, depends on the actual adopted criterion.

```text
HUMAN CDR FIRST-REVIEW RECORD: ILLUSTRATIVE DISPATCHER

1. Governing basis and scope
Project/component: illustrative dispatcher and separate worker/service.
Question: does the described job-dispatch recovery design have enough support
for commitment to implementing its automatic recovery behavior?
Actual governing criterion, edition, project-plan revision and applicability:
UNKNOWN. No NASA or defense criterion is asserted to govern this example.
Approved tailoring/equivalents/exceptions: UNKNOWN.
Scope: one request's dispatch and recovery. Job execution after starting and
other CDR categories are outside this thread; their actual owners are UNKNOWN.

2. Next commitment and authority
Illustrative commitment: implement automatic recovery for this dispatch.
Actual project commitment and authorized decision role/person: UNKNOWN.
Appointment status: not supplied.
Consequence of proceeding: implementation would depend on an unresolved
relationship between the receiver's effect and durable local dispatch knowledge.

3. Consequential requirement and effect
Illustrative rule: preserve one intended job for one approved request without
silently losing required work. This is not a supplied approved requirement.
Actual requirement identity/revision, approval and policy bounds: UNKNOWN.
Ordinary behavior: approved work results in the intended job starting.
Dispatch completion means the request to start work is complete; it does not
mean the job itself has completed.
Failure boundary: possible remote effect before durable local recording.
Consequence: an unintended repeated start, or required work silently omitted.
Actual timing/recovery bounds and permitted failure outcomes: UNKNOWN.
Proposed duty owner for those choices: requirement owner; UNASSIGNED.

4. Candidate and detailed-design decision
Reviewed location: the design description and possible sequence in this article.
Actual candidate design identity/revision: UNKNOWN.
Approved project baseline identity/status: UNKNOWN.
Described ordering: send the start-job request, then persist dispatch completion.
Restart may resend when local completion is absent.
Remote acceptance, effect, reply and durable local knowledge are distinct.
Receiver operation identity, effect durability, duplicate handling, concurrency,
retention and result/status-reconciliation guarantees: UNKNOWN.
The description does not establish how recovery resolves those unknowns.

5. Available evidence and its limit
Inspected material: the illustrative design description above.
Evidence type: documentary inspection.
Support: the described ordering exposes a point where external outcome and
durable local knowledge can diverge.
No implementation, receiver contract, execution record or observed effect exists
for this illustration. No repeat, loss, repair or retest was observed.
The possible sequence is reasoning about the description, not a captured trace.

6. Documentary finding
The described design does not establish recovery without an unintended repeat
or lost required operation.
A repeated effect is possible if the original took effect and the receiver
does not prevent the repeat. Missing local completion does not prove no effect.
Reversing the order can conceal omitted work after a crash before sending.
The gap matters to commitment to this automatic-recovery design.

7. Proposed correction and verification condition
Proposed work: obtain the real receiver contract and revise the state/interface
design to distinguish pending intent, known dispatch completion and uncertainty.
Define logical-operation identity, atomic/durable effect and duplicate handling,
applicable concurrency/retention, reply meaning and reconciliation behavior.
Preserve ordinary work; do not count always stopping or rejecting as success.
Implementation status: UNIMPLEMENTED.

Planned ordinary-success check:
  Expected: one intended job starts; durable dispatch knowledge matches the
  agreed receiver result, without asserting job completion.
  Distinguishes: blanket rejection, omitted work or unsupported local success.
  Needs: actual effect/acknowledgment contract and meaningful receiver evidence.
  Actual bounds and acceptance criteria: to be agreed; owners UNASSIGNED.
  Status: NOT EXECUTED.

Planned interruption/restart check:
  Interrupt after a possible remote effect but before durable local recording,
  then restart. Establish the original remote outcome and examine recovery.
  Expected: no additional unintended job start; local knowledge records the
  supported result or uncertainty awaiting an owned resolution step.
  Uncertainty is not completion. Resolution bounds and permitted failure
  outcomes remain for the requirement owner to establish.
  Distinguishes: repeated effect or unjustified certainty.
  Needs: receiver identity/durability/duplicate contract, applicable retention
  and concurrency guarantees, effect observation and controlled interruption.
  Actual bounds and acceptance criteria: to be agreed; owners UNASSIGNED.
  Status: NOT EXECUTED.

Planned uncertain-outcome check:
  Examine an applied request with a lost reply and a request with no effect.
  Expected: reconcile applied work; preserve and perform unapplied required
  work under the adopted recovery rule; record accurate local knowledge.
  Distinguishes: blind retry of applied work and silent loss of unapplied work.
  Needs: actual status/result semantics, external effect evidence and an owned
  decision for cases where safe reconciliation is unavailable.
  Actual bounds and acceptance criteria: to be agreed; owners UNASSIGNED.
  Status: NOT EXECUTED.

A caller stub can inspect transitions but cannot establish receiver guarantees.
A request ID, local transaction or outbox alone does not close this finding.

8. Responsibility and closure
Proposed duty owners, all UNASSIGNED:
  Requirement owner: required effect, bounds and permitted failure treatment.
  Receiver-interface owner: actual receiver contract and observable guarantees.
  Design owner: revised state/interface/recovery decisions.
  Verification owner: discriminating checks, prerequisites and retained results.
  Review lead: assemble the thread for the appointed decision authority.

Proposed closure for the affected implementation commitment:
  Review the receiver contract, revised candidate design and explicit checks.
  Identify which analysis/prototype evidence the governing criterion needs now
  and obtain it; identify later implementation checks and their review point.
  Record actual appointments, acceptance bounds and authorized disposition.
A clearer plan alone is not an implemented correction or passed retest.
Proposed review point: before authorizing the affected recovery commitment.
Later implementation evidence must be reviewed before relying on that behavior.
Actual schedule and authority to approve these conditions: UNKNOWN.
Reopen on relevant requirement, design, receiver-contract or recovery-bound changes.

9. Recommendation and authorized disposition
Illustrative reviewer recommendation: defer the commitment to implement the
affected automatic-recovery design pending the real receiver contract,
revised design and reviewable verification/closure conditions.
This recommendation does not decide unrelated, separately supported work.
Actual authority's disposition and decision record: UNRECORDED.
No authorized hold, permission to proceed or completed CDR is established.
Current status: documentary finding open; proposed correction UNIMPLEMENTED;
all proposed checks NOT EXECUTED; actual authority and appointments UNKNOWN.
```

**Use this on one actual decision:** copy the [worksheet](https://reqproof.com/topics/critical-design-review#worksheet), locate your design's corresponding failure boundary, and name the receiver evidence or other observation that would change your recommendation. A design-only review can identify that next action now.

## Follow the review in six steps

[Download the spoken transcript](https://reqproof.com/assets/critical-design-review/walkthrough-transcript.txt).

Read the narration and on-screen details

### 1. Name the next commitment

On screen

- One consequential requirement
- Candidate design revision
- Adopted review criterion
- Decision authority to identify

**Status:** Review method for an ILLUSTRATIVE thread; NOT EXECUTED; no authorization.

Narration

A critical design review asks whether the detailed design supports the next project commitment. Start with one consequential requirement, the candidate design revision, and a failure boundary. Use the free human record to connect the adopted review criterion, available evidence, missing support, responsible people, and the decision that still needs authority.

### 2. Understand the intended job

On screen

- Illustrative: one intended job
- Dispatcher asks a separate receiver
- Local record tracks dispatch
- Dispatch is not job completion

**Status:** ILLUSTRATIVE rule and design; NOT EXECUTED.

Narration

The illustrative rule is one intended job for one approved request, without silently losing required work. A dispatcher asks a separate worker service to start that job, then records dispatch completion locally. That record concerns the request to start work, not completion of the job itself.

### 3. Inspect the uncertain boundary

On screen

- Remote effect may precede recording
- Restart may resend
- Repeat depends on receiver behavior
- No duplicate was observed

**Status:** ILLUSTRATIVE possible failure path; NOT EXECUTED.

Narration

The receiver might start the job before the dispatcher durably records completion. After a restart, the missing local record might trigger another request. A repeated job is possible only if the original took effect and the receiver does not prevent the repeat. Nothing here was executed, and no duplicate was observed.

### 4. State the documentary finding

On screen

- Recovery support is incomplete
- Completion first can conceal loss
- Pending intent remains unfinished
- Receiver guarantees are unknown

**Status:** Documentary finding; ILLUSTRATIVE behavior, NOT EXECUTED.

Narration

The documentary finding is that this description does not establish recovery without an unintended repeat or lost required work. Recording completion before sending could instead hide a job that never started. A pending intention is different from completed dispatch. A request identifier alone does not establish the receiver's guarantees.

### 5. Plan discriminating observations

On screen

- Proposed ordinary-success check
- Proposed interruption and restart
- Proposed uncertain-outcome check
- External effect plus local knowledge

**Status:** PROPOSED correction and checks; UNIMPLEMENTED and NOT EXECUTED.

Narration

The proposed next work is to establish the receiver contract and revise recovery. Plan ordinary success, interruption after a possible remote effect but before local recording, and a missing reply when the request may or may not have taken effect. Check whether the intended job started and what the dispatcher durably knows after recovery. These checks are not executed, and no repair is implemented.

### 6. Keep recommendation and authority separate

On screen

- Recommendation concerns recovery implementation
- Contract and closure remain open
- Authorized disposition is unrecorded
- Bring a design-only question

**Status:** ILLUSTRATIVE reviewer recommendation; actual authorized disposition UNRECORDED.

Narration

The illustrative recommendation is to defer commitment to implementing this recovery design pending the receiver contract, revised design, and reviewable closure conditions. The actual authority and disposition are unrecorded. For your own design, name the missing observation, its owner, and the review point. A design-only packet is enough to start that discussion.

04 / Perform the review in order

## How to review one detailed-design claim

1. **Fix the decision boundary.** Identify the next implementation, integration or test commitment, the adopted criterion and the authority. Separate evidence needed now from work planned for later maturity.
2. **Select a consequential requirement.** State the ordinary required effect and what a wrong result would cost. Resolve disputed intent with its owner; do not derive the requirement from today's implementation.
3. **Identify the candidate.** Locate the actual design revision and its relationship to the approved baseline. Follow the requirement into the state, interface, algorithm or resource decision that must satisfy it.
4. **Walk the failure boundary.** Ask what each component has done, what it knows, what survives interruption and what recovery is allowed to conclude. Expose assumptions crossing component or supplier boundaries.
5. **Inspect the available support.** Distinguish design inspection, analysis, supplied execution evidence and proposed checks. Explain what each supports and which dependency, changed revision or missing observation limits it.
6. **Specify the smallest discriminating next check.** Name the expected effect, relevant local state, plausible wrong result, prerequisites and acceptance rule. Include ordinary success when a protective change could prevent required work.
7. **Take an owned finding to the authority.** Record the proposed correction, closure evidence, review point and recommendation. Keep the actual disposition separate, then reassess affected evidence when its basis changes.

05 / Check the handoff

## Before calling the thread ready for a decision

- The adopted criterion and its revision are identifiable.
- The next commitment and responsible authority are explicit.
- The required effect and candidate design revision are connected.
- State, interface and durability assumptions are visible.
- Evidence supports the claimed scope; missing support remains open.
- Proposed observations distinguish success from the relevant wrong result.
- Each closure action has an appointed owner or an explicit vacancy.
- The authorized disposition is recorded, or clearly unrecorded.

This handoff checklist organizes the thread for judgment; the project's CDR criteria still govern.

06 / Repair misleading review evidence

## CDR mistakes that hide unfinished decisions

**Different ways a plausible review package can overstate its support.**

Mistake / Why it misleads / Repair

| Mistake | Why it misleads | Repair |
| --- | --- | --- |
| Call the candidate an approved baseline | Review comments and configuration decisions disappear from the record. | Identify the candidate separately and record formal baselining at the applicable point. |
| Treat a linked test or green build as behavioral evidence | Neither establishes that the relevant failure boundary was exercised or its effect observed. | Inspect the assertion, actual evidence and scope needed by the design claim. |
| Accept agreement among generated design, code and tests | They can repeat the same unsupported assumption. | Derive the expected behavior from the approved requirement and inspect the dependency contract independently. |
| Turn a supplier capability label into a local guarantee | “Idempotent” alone leaves operation identity, effect and recovery limits unresolved. | Obtain the actual applicable interface contract and its supporting evidence. |
| Delete a difficult obligation during review | The apparent improvement comes from changing the acceptance basis. | Retain the original gap and obtain an authorized requirement or scope decision. |
| Treat the meeting's end as approval | Actions, residual risk and authority remain unresolved. | Record the process-required disposition and closure controls. |

Historical AI use is unknown for the illustration. These sources do not establish a blanket CDR mandate for AI-assisted coding.

07 / Use Proof within its scope

## Use connected evidence without delegating the CDR decision

Proof helps maintain intent and inspect connected requirements and evidence; your team designs and builds the system. Its [public workflow](https://reqproof.com/agents) describes bringing that context to people and coding agents.

For a configured project, Proof's CDR gate checks preparation such as annotations/lint, links and trace validity, build and orphan links. It does not semantically review every state, interface or failure path, adopt government criteria, approve CDR or authorize the next phase. No command ran for this illustration.

08 / Choose the method for the gap

## Which review method will answer the unresolved question?

Choose the method for the unresolved claim. Each option below has a different evidence boundary.

**Method choices for a bounded detailed-design decision.**

Unresolved question / Useful next method / What it can establish and leave open

| Unresolved question | Useful next method | What it can establish and leave open |
| --- | --- | --- |
| Is the detailed behavior actually specified? | Review the requirement beside a state/transition table and interface description. | Exposes missing decisions and contradictions. It supplies documentary support, not runtime behavior. [NASA software review guidance](https://swehb.nasa.gov/spaces/SWEHBVD/pages/102695639/7.09+-+Entrance+and+Exit+Criteria) |
| Does the receiver support the proposed recovery contract? | Inspect the actual receiver specification and supporting evidence with its interface owner. | Establishes which guarantees may be relied on. An engineering article or caller stub cannot supply an absent provider guarantee. [AWS method context](https://aws.amazon.com/builders-library/making-retries-safe-with-idempotent-APIs/) |
| Can the proposed design satisfy the claim under explicit assumptions? | Targeted analysis, modeling or a prototype suited to the uncertainty. | Supports the analyzed model or demonstrated conditions; assumptions and implementation differences remain visible. [Defense CDR guidance](https://www.cto.mil/wp-content/uploads/2026/09/SE-Guidebook-2026.pdf) |
| Does implemented recovery preserve the external effect? | Controlled integration and interruption checks against the identified receiver, with effect and recovered-state observations. | Supports the selected cases and conditions. Plan readiness, actual results and acceptance remain separate. [NASA CDR planning context](https://nodis3.gsfc.nasa.gov/displayDir.cfm?Internal_ID=N_PR_7123_001D_&page_name=AppendixG) |

Use the worksheet in the versioned review document or issue your team already maintains. A model or finite test campaign can support a bounded claim; neither establishes universal production correctness or certification.

09 / Establish the actual review basis

## Primary sources, editions and applicability

Record the **source edition, adopted project criterion and reviewed candidate separately**. First locate the governing contract and lifecycle plan. Then identify the clauses and approved tailoring relevant to this commitment. Finally, inspect the complete criteria and their referenced products; an excerpt or a source link does not establish conformance.

### Current review sources

Source and edition / What to inspect / Interpretation boundary

| Source and edition | What to inspect | Interpretation boundary |
| --- | --- | --- |
| [Systems Engineering Guidebook, September 2026](https://www.cto.mil/wp-content/uploads/2026/09/SE-Guidebook-2026.pdf) | §5.7 and Table 5-5, printed pp. 75–81; §5.2, p. 58. The [official index](https://www.cto.mil/sea/pg/) identifies the 2026 edition. | Detailed-design maturity and the initial product baseline can support production software coding under configuration management. A complete-system demonstration is not expected, but relevant analyses and prototype evidence still matter. Control of the initial product baseline does not itself mean delivery and acceptance of the technical data package. |
| [DoDI 5000.88, Engineering of Defense Systems, 18 November 2020](https://www.esd.whs.mil/Portals/54/Documents/DD/issuances/dodi/500088p.PDF) | §§1.1–1.2 and §3.5.a. | Applies within its stated DoD scope. Account for acquisition-pathway tailoring, the adopted Systems Engineering Plan (SEP), equivalent reviews and authorized waivers. Do not infer universal contractor flowdown. |
| [NASA NPR 7123.1D, Updated w/Change 2](https://nodis3.gsfc.nasa.gov/displayDir.cfm?Internal_ID=N_PR_7123_001D_&page_name=Chapter5) | Effective 5 July 2023; [Change 2 approved 20 February 2024](https://nodis3.gsfc.nasa.gov/displayDir.cfm?Internal_ID=N_PR_7123_001D_&page_name=ChangeLog). Read §5.2.2.2.e, §5.2.2.4 and [applicability in P.2](https://nodis3.gsfc.nasa.gov/displayDir.cfm?Internal_ID=N_PR_7123_001D_&page_name=Preface). | SE-46 requires the minimum detailed-design baseline product within applicability. Final drafts enter review; approved comments are incorporated before formal baselining. Apply P.2, including its NASA/support-contractor scope and other-party contract/agreement limits. |
| [NPR 7123.1D Appendix G](https://nodis3.gsfc.nasa.gov/displayDir.cfm?Internal_ID=N_PR_7123_001D_&page_name=AppendixG) | G.1, G.8 and Table G-7, alongside Chapter 5. | Recommended/customized criteria do not erase the SE-46 minimum. Complete V&V requirements and plans do not mean every final verification result is complete. Applicable analyses, engineering units and tests per plan still matter. |
| [NASA Software Engineering Handbook, Version D, Topic 7.09, page 102695639](https://swehb.nasa.gov/spaces/SWEHBVD/pages/102695639/7.09+-+Entrance+and+Exit+Criteria), and [PAT-072 CDR checklist, attachment version 8](https://swehb.nasa.gov/download/attachments/204079258/PAT-072%20-%20CDR%20-%20Software%20Critical%20Design%20Milestone%20Review%20Checklist.docx?version=8&modificationDate=1791917482000&api=v2) | The introduction, §8 and the project's tailored checklist. | Recommended software-review guidance and a tailorable aid. Numerical thresholds, IV&V conditions and Synthetic Intelligence items are not universal requirements for every CDR or coding-assistant project. The PAT does not substitute for governing requirements. |

### Keep closure rules separately attributed

**NASA:** Table G-7 permits timely closure plans for specified remaining review discrepancies or action requests. Section 5.2.3.1 requires agreed dispositions, completion records and follow-through controls, including the Program/Project Decision Authority's signed decision memo. [Appendix G](https://nodis3.gsfc.nasa.gov/displayDir.cfm?Internal_ID=N_PR_7123_001D_&page_name=AppendixG) · [Chapter 5](https://nodis3.gsfc.nasa.gov/displayDir.cfm?Internal_ID=N_PR_7123_001D_&page_name=Chapter5)

**Defense:** §5.7's entrance criteria concern completed prior reviews and closed prior actions against the SEP criteria. Section 5.2 expects criteria achieved and actions closed for review completion. Section 5.7 also lists corrective-action plans among CDR outputs and recognizes that some supporting-system baselines can lag; the review chair determines completion and the assessment informs the decision authority. [September 2026 guidebook](https://www.cto.mil/wp-content/uploads/2026/09/SE-Guidebook-2026.pdf)

These provisions do not create a universal “pass with a plan” rule or a prohibition on every form of remaining work. Apply the actual rule to the affected scope and commitment.

### Explanatory and technical sources

- [NASA/SP-2016-6105 Rev 2, NASA Systems Engineering Handbook](https://www.nasa.gov/wp-content/uploads/2018/09/nasa_systems_engineering_handbook_0.pdf), Table 6.7-1, printed p. 162: historical explanation of CDR in NASA's lifecycle, not a newly issued 2026 standard.
- [RFC 9110, HTTP Semantics, June 2022, §9.2.2](https://www.rfc-editor.org/rfc/rfc9110.html#section-9.2.2): HTTP-specific intended-effect and retry semantics. Idempotence concerns the requested server effect; replies need not be identical.
- [Malcolm Featonby, AWS Builders' Library, Making retries safe with idempotent APIs](https://aws.amazon.com/builders-library/making-retries-safe-with-idempotent-APIs/): engineering explanation of operation identity, receiver-side atomicity, result meaning, late requests, retention and changed intent. It supplies questions for this design, not its actual receiver contract.

10 / Apply the method to another uncertainty

## Two more detailed-design decisions

### An interface agrees on the field type but not the unit

**Illustrative design review; checks NOT EXECUTED.** A controller supplies a duration to a worker. Both describe it as an integer, but the interface does not establish whether it means seconds or milliseconds. Type compatibility cannot establish correct timing.

Before committing to the adapter implementation, the interface owners should settle the unit, conversion, range and invalid-value behavior. The proposed check compares the duration interpreted at the worker with the requirement's intended duration, including agreed boundaries. Actual values and acceptance bounds remain unset. A successful build would leave this interface decision unresolved.

### A resource margin depends on an unstated workload

**Illustrative analysis plan; NOT EXECUTED.** A detailed design promises to retain pending work within its allocated memory, but its sizing argument omits how much work can arrive while the receiver is unavailable. A positive-looking margin has no defined workload basis.

Before committing to that resource allocation, the requirement and design owners should set the arrival, outage, retention and overflow assumptions, then assess the candidate design against them. The proposed evidence is a reviewable capacity argument and any targeted measurement the adopted criteria require. No workload, margin or result is supplied here. This decision needs an explicit resource model before a useful test can be specified.

11 / Resolve the remaining questions

## Critical design review questions, answered

Can a team without a formal CDR meeting use this record?

Yes. Put the thread in the design review or change process that actually governs the commitment. Name who can decide and what support they need. Using this aid does not claim completion of a government milestone.

What if the requirement itself is disputed?

Record the competing interpretations and their consequences, then assign the decision to the responsible requirement owner. Continue inspecting the design, but do not label one interpretation “verified” merely because the implementation or a generated test agrees with it.

What if the receiver contract cannot be obtained?

Keep the dependency open. A caller stub may help develop local logic, but it cannot close a claim that depends on unknown receiver guarantees. Ask the authority to assess the affected commitment using that explicit uncertainty and any proposed alternative design.

Can only part of the design proceed?

That depends on the adopted process and authority. Identify the supported portion, its interfaces with unresolved work and the consequence of proceeding. Record any authorized scope and conditions; one thread's recommendation cannot authorize or halt unrelated work.

What if the design changes after the review?

Identify which requirements, assumptions, analyses, interfaces and planned checks the change affects. Update the controlled records and obtain the required review or disposition. A previous review outcome should not silently attach to a different candidate.

12 / Continue with the right guide

## Related guides

- [Preliminary design review](https://reqproof.com/topics/preliminary-design-review): assess architecture feasibility before the detailed decisions examined here.
- [Test readiness review](https://reqproof.com/topics/test-readiness-review): decide whether a specified campaign can produce usable evidence.
- [Software verification plan](https://reqproof.com/topics/software-verification-plan): organize several open checks with methods, criteria and owners.
- [Requirements-based testing](https://reqproof.com/topics/requirements-based-testing): derive observations from the required behavior.
- [PoC review checklist](https://reqproof.com/topics/poc-quality-checked): assess what a prototype actually supports before reusing it as design evidence.
- [MC/DC coverage](https://reqproof.com/topics/mcdc-coverage): understand one form of structural evidence and the behavioral questions it leaves open.

## Bring one detailed-design decision to its next review

**Commitment and basis.** One non-sensitive requirement, candidate design revision, governing criterion and actual next commitment.

**Failure and evidence.** The failure/recovery uncertainty, available support and observation still needed.

**Responsibility and decision.** Responsible people or unresolved appointments, proposed closure conditions and the authority's disposition, if recorded.

[Review one detailed-design decision with Proof](https://reqproof.com/demo?engagement=audit&interest=correctness). A design-only packet is welcome when implementation does not yet exist.

Free CDR first-review record

**01** **Commitment and basis** One non-sensitive requirement, candidate design revision, governing criterion and actual next commitment.

**02** **Failure and evidence** The failure/recovery uncertainty, available support and observation still needed.

**03** **Responsibility and decision** Responsible people or unresolved appointments, proposed closure conditions and the authority's disposition, if recorded.